The military technological college located in Muscat, has an olympic size pool 50x25m.
City: Muscat, Oman
Project carried out by: Al Ansari
City: Muscat, Oman
Project carried out by: Al Ansari
The military technological college located in Muscat, has an olympic size pool 50x25m. The filtration of this pool is carried out by 6 pumps FDN-126H in bronze, giving a flow of 241m³/h at 10 wmh each, ensuring that all the water of the pool is filtered in 2.5 hours. These FDN-126H bronze pumps constructed in casted Rg5 bronze, make these pumps very robust to work in all conditions.
The 1450 rpm motors guarantee a long life of the pumps and the eficiency above 70% ensures important energy savings for the college. The reduced noise level offers comfort for the pool users.